Archive for the ‘Civil Litigation, General’ Category

Time Limits Prevent Flooding and Damp Claim

Friday, June 24th, 2011

A couple who had large-scale alterations to their house done, including the creation of a substantial basement room, found that the basement suffered from substantial water penetration, which commenced shortly after it was completed in 2001.

 
The ingress of water necessitated substantial remedial work. However, between 2002 and 2008, however, damp sports appeared and the problem worsened. By the summer of 2008, water was beginning to accumulate under the floor.
 
The homeowners commenced legal proceedings against the architects and builders in 2010. Various claims were made, of which almost all related to the original construction work done. The defendants argued that the couple’s claim was ‘out of time’ under the Limitation Act.
 
The builder argued that a claim for breach of contract would have had to be brought by 2008 (six years after the date of the relevant breach). A claim in tort (i.e. for damages due to a civil wrong) would have to be brought within three years of the damage for which compensation is sought occurring. The damage initially occurred between late 2001 and the March 2002, making a claim after March 2005 ‘out of time’.
 
The couple argued that they did not have sufficient knowledge to commence a claim until 2007, so the claims were ‘in time’.
 
The starting date for making such a claim is the ‘earliest date’ on which the claimant had the knowledge of sufficient essential facts to bring a claim in damages or to take advice about bringing a claim.
 
The judge concluded that the couple had sufficient knowledge  in 2002 to ‘set the clock running’ with regard to all the claims relating to the original construction work. Those claims were therefore out of time and failed. The two claims that related to the rectification work could be argued to be ‘in time’ and remain to be tried in court.
 
When you discover a problem which may lead to a claim in damages, it is essential to act promptly. Failure to do so can be a very expensive error if it leads to the court refusing to hear a claim because it has not been brought in time.

 

Ombudsman Orders Compensation Following Planning Approval

Friday, May 27th, 2011
A Council that took account of the personal circumstances of an applicant for planning permission, when granting an application to construct a bungalow outside the designated development area and in green belt land, has been criticised by the Local Government Ombudsman.
 
The person who applied for permission to build the bungalow was elderly, disabled and owned a home which was susceptible to flooding. Melton Borough Council granted planning permission despite the objections of the owners of adjoining land and even though the application was contrary to the Council’s stated planning policies and went against the recommendation of the planning officer who had reviewed the application.
 
The Ombudsman ruled that the owners of the adjoining land should be compensated for the diminution in value of their property as a result of planning permission being granted and awarded an additional £500 for their time and trouble in raising the complaint.
 

If it is in the Sky, It is Weather!

Friday, May 20th, 2011

Plane on runway

The Financial Services Ombudsman has refused to refer a test case involving a travel insurance claim to the court in order to determine whether the volcanic ash cloud which caused so much disruption to European aviation in 2010 was not covered by the phrase ‘poor weather conditions’.
 
Most travel insurance policies contain limitations in cover which exclude or limit claims resulting from ‘acts of God and those relating to areas where there is civil unrest or war or to which travel is undertaken when the Foreign Office has advised against it. Normally, they allow a claim to be made where it results from adverse weather conditions.
 
The case involved a woman whose claim was refused by the insurer, which argued that it was not covered by the clause that allowed a claim to be made when the travel disruption resulted from adverse weather conditions. She appealed to the Ombudsman.
 
The ombudsman concluded that it was not a suitable case to refer to the court as a test case and made an award to the claimant.

Banks Give in Over PPI

Thursday, May 19th, 2011
Payment Protection Insurance (PPI), which was sold aggressively by many of the clearing banks during the debt boomCommercial property 1110 of the 1980s and 1990s, has led to large provisions being made for losses as the banks have abandoned attempts to fight mis-selling claims.
 
Thousands of customers w ere sold PPI policies, which undertook to cover loan repayments on lo an in the event that the borrower became unemployed or fell ill and was unable to make the repayments. The policies were extremely profitable for the banks because the claim rates were very low and the policy costs were high.
 
However, following widespread complaints and successful litigation, the banks have abandoned their struggle and have earmarked more than £5 billion to meet claims.
 
 

Claim Procedure Reforms Will Affect Smaller Claims

Thursday, April 28th, 2011

 Stafford CourtWith all the hoop-la about the proposed change to the ‘no win, no fee’ regime, another set of proposals, which may well be of greater importance for many people has slipped under the radar of the popular press.

 
A new consultation paper proposes changes to the limits on claims to be heard by the lower courts. The proposals include:
 
  • the limit of a claim which can be dealt with in the small claims court is to be increased from the current £5,000 to £15,000; and
  • the minimum limit for a case to be sent to the High Court is to be raised from £25,000 to £100,000; and
 
In addition, the online system for settlement of smaller road traffic accident cases is to be adapted for use in all small personal injury cases up to £50,000 in value and trialled for use in claims for clinical negligence against the NHS.

Banks Receive PPI Compensation Setback

Tuesday, April 26th, 2011

Offixe 23The long-running battle between banks and their customers over alleged mis-selling of payment protection insurance (PPI) plans took another step forward last week when the High Court dismissed a challenge brought by the banks that guidance on such policies issued by the Financial Services Authority on sales of insurance did not apply to PPI policies.

 
PPI policies were sold aggressively by banks to customers who took out loans. They insure the person taking the loan against redundancy and illness, with the insurer covering any loan payments due during the period of incapacity or unemployment. The cost of the policy was normally added to the loan on day one, meaning that if the debt was paid off early, premiums had been paid unnecessarily. Typically, a PPI policy would add more than 20 per cent to the loan.
 
The move paves the way for customers to receive refunds of premiums paid. However, an appeal by the banks is likely and, even if unsuccessful, the estimated £4.5 billion cost will inevitably end up being met by the current customers of the banks, most probably through the demise of free bank accounts.
 

If you have suffered a loss through being mis-sold a financial product, you may be able to obtain redress. Contact us for advice